ACATS Fixed Trunk MTP2 Framework Test Suite
TEST SUITE OVERVIEW
References
Archive/Projectss7/mtp2_FTS
Version20.07.36.01
Date12 Feb 2009
Number of Scenarios10
Number of Groups8
Average per Group1
GROUP/SCENARIOTEST PURPOSE
Link_State_Control_01Link State Control – Expected signal units/orders
SC_01_01To check that the No. 7 terminal equipment enters the correct state on power-up.
SC_01_05To check normal alignment procedure
Link_State_Control_02Link State Control – Unexpected signal units/orders
SC_02_01To check that the unexpected signal units/orders are ignored ("Out of service" state)
SC_02_02To check that the unexpected signal units/orders are ignored ("Not aligned" state)
Transmission_failure_03Transmission Failure
SC_03_01Test response to transmission failure – detected by SUERM – when in "Aligned ready" state
SUERM_check_06SUERM Check
SC_06_04To check response to a range of time controlled breaks of Tx or Rx
AERM_check_07AERM Check
SC_07_01To test the AERM on error rates below the normal threshold
Transmission_and_reception_control_Basic_08Transmission Control
SC_08_04To ensure correct performance when an MSU with erroneous FIB is received
Transmission_and_reception_control_PCR_09Transmission PCR
SC_09_07To ensure correct performance while RPO is set
Congestion_Control_10Congestion Control
SC_10_02To check timer T7 is restarted at the reception of SIB (without expiring of T6)

VariableDefault ValueDescription
ANSIFALSE(null)
MSU_NI_VNational_Network_C(null)
MSU_OPC_V14441(null)
MSU_DPC_V14425(null)
MSU_SLS_V1(null)

Copyright © ACATS Forum 2010 on behalf of the test suite author. All rights reserved. Specifications may change subject to requirements.

08 Jan 2010Produced by SAFIRE V20.07.36.01